Agratas Hits Key Construction Milestone at Sanand Battery Facility Ahead of 2027 Production

The Tata Group's battery unit has finished the main structural frame at its Gujarat facility, which will have a 20 GWh annual capacity in its first phase.

02 Apr 2026 | 1988 Views | By Sarthak Mahajan

Agratas, the Tata Group's global battery business, has completed the steel frame at its battery manufacturing facility in Sanand, Gujarat, marking a significant construction milestone as the company works toward beginning production in 2027.

The completed structure spans 700 metres in length and 150 metres in width, rising to 34 metres at its peak and covering a built-up area of 105,000 square metres. The main structure required over 24,000 tonnes of steel, with more than 2,500 workers on-site at peak construction. The project is being executed by Tata Projects Limited, alongside Tata Consulting Engineers, with steel and the majority of other materials sourced domestically from across India.

Once operational, the Sanand facility will produce advanced battery cells for electric vehicles and energy storage applications, with a planned first-phase annual capacity of 20 GWh. The company has positioned the facility as central to India's broader clean energy ambitions, including the country's targets of achieving net zero emissions by 2070 and 500 GW of non-fossil fuel energy capacity by 2030.

The project is also expected to create substantial regional employment across production, operations, engineering, maintenance, and quality assurance roles, with Agratas committing to local workforce development programs.

Agratas is simultaneously developing a second battery manufacturing facility in Bridgwater, UK, as part of its global industrialisation strategy.

RELATED ARTICLES

Hyundai Registrations Rise 30% to Nearly 41,000 during Shradh and Navratri

Mukul Yudhveer Singh 21 Oct 2026

Hyundai Motor India reports strong festive demand across urban and rural markets, with bookings expected to sustain mome...

Bondada Group Enters EV Market via Atpole-Thuraga Partnership; Pre-Bookings Open for T1 E2W

Eshisha Java 21 Oct 2026

B2B and B2C electric two-wheeler priced at Rs 59,999; commercial availability scheduled for November 2026 across souther...

JLR to Launch Electric Versions of the Range Rover and the Sport as Full Imports

Autocar Professional Bureau 21 Oct 2026

While the brand locally assembles ICE versions of the Range Rover and Range Rover Sport, the electric avatars would arri...

Tags: Tata Group
NEXT STORY