SKF India has outlined a phased investment of INR 1,404 million towards capacity expansion at its Pune and Haridwar manufacturing plants. The investment will support the addition and enhancement of four production channels across the two facilities, with production scheduled to commence in stages between December 2026 and July 2027.
The expansion comprises an investment of INR 626 million at the Haridwar plant and INR 778 million at Pune. The company will fund both projects through internal accruals.
At Haridwar, SKF India plans to add two production channels for its DGBB (Deep Groove Ball Bearing) operations. The plant currently has four production channels, operating at approximately 90% capacity utilisation.
The first additional channel will involve an investment of INR 247 million, with production scheduled to begin from December 2026. The second channel will require INR 379 million, with production expected to commence from March 2027.
At the Pune plant, the expansion will focus on the TRB (Tapered Roller Bearing) channel. The facility currently operates six production channels at approximately 85% capacity utilisation.
The proposed additions comprise capacity enhancement through machine addition for one channel, followed by the addition of another production channel. The first phase will involve an investment of INR 347 million, with production scheduled to begin from March 2027. The second phase will require INR 431 million, with production expected to commence from July 2027.
SKF India said the capacity additions are intended to support customer demand and reduce trading volumes. Both projects will be financed through internal accruals.