Mumbai-Nagpur highway opening pushed to 2024

It was scheduled to open early next month

30 Sep 2024 | 6101 Views | By Amit Vijay M

The Maharashtra government's flagship project, the Maharashtra Samruddhi Mahamarg connecting Mumbai to Nagpur, which was originally scheduled to open early next month, is facing delays due to a 1-kilometer bottleneck near Mumbai, pushing the deadline for the 701-kilometer project’s completion to early next year.

"Several factories and warehouses need to be demolished along this 1-kilometer stretch, which will serve as the endpoint of the Samruddhi Mahamarg. This is necessary to finish the last 4.5 kilometers of the road, of which 3.5 kilometers are already complete, linking the village of Amane to the Shangrila Resort on the old Mumbai-Nashik Highway," sources in MSRDC stated. 

The Maharashtra government had initially expected the 76-kilometer stretch, critical for opening the Nagpur-Mumbai Motorway, to be finished by the first week of August. This would have enabled the highway to open in September, but the delay has now shifted the timeline.

RELATED ARTICLES

Suzuki Motorcycle India Opens First Dealership in Sirsa

Angitha Suresh 30 May 2026

The new outlet in Haryana's Sirsa district brings the company's national dealer network to 1,246 touchpoints, with 25 no...

India's Passenger EV Market Set for Breakout Year; Sales Could Reach 400,000 Units in FY27

Autocar Professional Bureau 30 May 2026

Automakers expand production amid surging bookings, with industry penetration expected to nearly double from FY26 levels...

Olectra Greentech FY26 Net Profit up 29% to ₹179.5 crore

Arunima Pal 29 May 2026

The company delivered 1,280 electric vehicles during the year, up 32% from 972 units in FY25.

NEXT STORY