Girder installation near Anandnagar completed, to help smoothen traffic congestion in Mumbai
Upgrade of the current 2+2 lane bridge to 4+4 will benefit both small and heavy vehicles on the expressway.
The installation of a critical girder at the Anandnagar subway rail over bridge near Kopri along the Eastern Expressway was completed on Sunday, according to the commissioner of MMRDA.
He added that the project will result in the upgrade of the current 2+2 lane bridge to 4+4, benefiting both small and heavy vehicles on the expressway and reducing traffic congestion.

The MMRDA officials stated that the authority and contractors employed a total of 50 people during the actual girder erection, which occurred between Saturday and Sunday night. Two cranes with a capacity of 200 tonnes were used, with an additional one kept as a spare. A couple of 100-ton cranes were also used to place the girders. The girder construction completed 85 percent of the project.
MMRDA will bear the entire project cost, which is expected to exceed Rs 258 crore, the officials remarked.
The Mumbai Metropolitan Region Development Authority (MMRDA) is responsible for developing plans, policies, and programmes, implementing projects, and guiding investment in and around the Mumbai region.
RELATED ARTICLES
Leanwatts Raises $2 Mn Seed Funding to Scale EV Power Electronics Manufacturing
The Hyderabad-based company plans to use the funding to expand manufacturing capacity, strengthen R&D and testing infras...
Ather’s Konarc Bet Signals a Push Into Mainstream Growth
Ather’s challenge with Konarc is to enter a significantly larger and more price-sensitive part of the market without giv...
Ather Targets to Expand Retail Footprint to Upto 2,000 Stores in 2 Years
The company will start deliveries of new Konarc scooter in September while it will unlock capacity with the new Aurangab...


30 Oct 2022
5154 Views
Shruti Shiraguppi

Kiran Murali