Girder installation near Anandnagar completed, to help smoothen traffic congestion in Mumbai
Upgrade of the current 2+2 lane bridge to 4+4 will benefit both small and heavy vehicles on the expressway.
The installation of a critical girder at the Anandnagar subway rail over bridge near Kopri along the Eastern Expressway was completed on Sunday, according to the commissioner of MMRDA.
He added that the project will result in the upgrade of the current 2+2 lane bridge to 4+4, benefiting both small and heavy vehicles on the expressway and reducing traffic congestion.

The MMRDA officials stated that the authority and contractors employed a total of 50 people during the actual girder erection, which occurred between Saturday and Sunday night. Two cranes with a capacity of 200 tonnes were used, with an additional one kept as a spare. A couple of 100-ton cranes were also used to place the girders. The girder construction completed 85 percent of the project.
MMRDA will bear the entire project cost, which is expected to exceed Rs 258 crore, the officials remarked.
The Mumbai Metropolitan Region Development Authority (MMRDA) is responsible for developing plans, policies, and programmes, implementing projects, and guiding investment in and around the Mumbai region.
RELATED ARTICLES
JSW MG Targets Over 1 Lakh Sales in 2026, Bets on Hector Tomahawk to Drive Growth
JSW MG plans 42% volume growth this year, banking on 6,000 monthly Hector Tomahawk units and plug-in hybrid adoption to ...
Third-Gen Audi Q3 Makes India Debut Ahead of Launch
The new Q3 gets a sharper design, a more tech-focused cabin and a larger footprint; India launch is expected later this ...
L&T Signs Distribution Agreement with FAYAT to Market BOMAG Road Equipment in India
Partnership covers sales, spare parts distribution, and lifecycle servicing for German-engineered milling machines, soil...


30 Oct 2022
5150 Views

Autocar Professional Bureau